- Submit PSC form 6027 & 6029 to utilities, Dawn Gall at dgall [at] cityofelkhorn.org (dgall[at]cityofelkhorn[dot]org) along with CAD and insurance documentation
- Obtain Wisconsin Uniform Building Permit Application – Click Here
- Receive approval from utilities via email for PSC 6027 & 6029
- Contact Building & Zoning when ready and an inspector will go into the field and bring the paperwork back to the office
- Call Electric Utilities at 262-723-3138 to have service disconnected, if needed, and to install a new, bi-directional meter
- The Building Inspector will inspect
- Call Electric Utilities at 262-723-3138 to re-connect
** City of Elkhorn follows Alliant Service and Equipment Rules **
FAQ:
- Is the residential limit size for solar systems still 20 kW? Yes
- Is the commercial limit size for solar systems still 40 kW? No
- Is there an interconnection application fee? No
- Is the best way to submit interconnection applications still via email? Yes
- What is the best email/contact to send these applications to? dgall [at] cityofelkhorn.org (dgall[at]cityofelkhorn[dot]org)
- Is the overproduction payout still “single rate retail annual forced payout”? Yes, 100%
- Is there currently an incentive/rebate program? No
- Do you use net meters or production meters? Bi-directional meter, AMI
- Is your interconnection type load side or line side? Load side
- Is the conductor from the transformer maintained by Elkhorn Light & Water or the homeowner? Elkhorn Light & Water
- How far in advance should we be scheduling these disconnects/reconnects? 2 weeks
- What is the maximum number of disconnects we are able to schedule in a single day? 1
- Is an electrical inspection required before reconnecting? Yes
- What are the earliest and latest times we are able to schedule a disconnect? 7:00 am – 3:00 pm